The North Carolina Utilities Commission has approved a two-step electric rate increase for Duke Energy Carolinas, and Charlotte customers will see higher bills starting January 1.
For a typical residential customer using 1,000 kilowatt-hours a month, the increase amounts to $6.53 a month from January 1, 2027, and another $4.66 a month from January 1, 2028, according to Duke Energy. That is about 9.5 percent over two years.
The decision covers both of Duke Energy’s North Carolina utilities. Duke Energy Progress, which serves central and eastern North Carolina and the Asheville area, has received approval for an average annual increase of 3.4 percent over two years, or 4.7 percent for residential customers. A typical Progress residential customer using 1,000 kilowatt-hours a month will pay $9.62 more from January 1, 2027, and $5.89 more from January 1, 2028.
A request cut roughly in half
Duke Energy filed the rate cases on November 20, 2025, asking for far more. The original request would have raised residential rates by about 18 percent over two years, with Duke Energy Carolinas seeking about $1 billion a year in additional revenue and a return on equity of 10.95 percent.
Customers pushed back. In June, Duke Energy lowered its own request, bringing the residential increase down to 11.6 percent. In July, Duke Energy Carolinas reached a settlement with the commission’s Public Staff — the agency that represents utility customers — along with the Carolina Industrial Group for Fair Utility Rates, the Carolina Utility Customers Association, the North Carolina Sustainable Energy Association, and Walmart. Duke Energy Progress reached a similar settlement in August. The commission has now approved those settlements, with the approved increase amounting to roughly half of what Duke Energy first asked for.
“We listened to our customers and worked closely with stakeholders to find a more cost-effective way forward,” said Kendal Bowman, Duke Energy’s North Carolina president. “This outcome keeps affordability at the forefront while allowing us to make the investments needed to strengthen reliability and support North Carolina’s continued growth. That balance is what we were working to achieve.”
According to Duke Energy, North Carolina ranks third in the nation in population growth, adding nearly 150,000 residents last year, and has ranked first or second for business in each of the last six years. The company says the rate increase pays for grid work including 116,430 distribution poles and 24 million feet of wire added or replaced over the last five years, along with self-healing technology that now covers more than 80 percent of its North Carolina customers.
The orders set Duke Energy Carolinas’ return on equity — the profit rate regulators allow on the company’s investments — at 9.8 percent, with a 53 percent equity component, and a retail rate base of about $25.7 billion. The projected two-year revenue increase is $496 million for Duke Energy Carolinas and $338 million for Duke Energy Progress, subject to final calculations with the Public Staff.
Data centers will pay more upfront
The orders also create a new rate schedule for data-center customers with loads above 50 megawatts, with upfront payments for dedicated facilities, financial requirements for transmission upgrades, and security requirements to guard against stranded generation investments.
The new terms require minimum contract terms of 10 years, or at least 15 years for facilities of 100 megawatts or more, and demand charges based on at least 75 percent of contracted power even if it goes unused. The orders also set a stranded-generation charge of about $67,357 per megawatt-year. About 7.9 gigawatts of potential large-load demand is in advanced development across the two utilities, according to the commission’s orders.
The commission changed the large-load settlement the parties proposed in October rather than adopting it unchanged. Duke Energy has said it is “still assessing that portion of the Orders.” A stakeholder process will now work out a standard energy service agreement and the methods for assigning transmission-upgrade costs and stranded-generation charges.
Protections written into the orders
The orders include a multiyear rate plan refund rider: if Duke Energy does not complete planned infrastructure upgrades on time, money goes back to customers, with interest.
Duke Energy shareholders will also contribute $20 million — $10 million at each utility — to low-income bill assistance and weatherization programs, on top of existing funding. Duke Energy also agreed to lower customer costs for reliability upgrades at its Belews Creek plant because of federal funding.
Duke Energy and Progress will combine into a single utility on January 1, 2027, but rates will remain separate. Rates will start to blend gradually over time at a pace set by the commission in future rate cases and rider filings, according to Duke Energy.
Critics say it still asks too much
Not everyone is satisfied. The North Carolina Justice Center, the North Carolina Housing Coalition, the Southern Alliance for Clean Energy and Vote Solar — represented by the Southern Environmental Law Center — opposed the original requests and say the approved 9.8 percent return on equity is too high. They had proposed 9.1 percent, which they say could have saved ratepayers as much as $280 million.
“The commission’s rulings unfortunately raise electricity rates for North Carolinians but keep them lower than Duke’s proposed rate hikes and chart a potential pathway to tamp down future rate hikes that stem from large customer power demand and ensure that the utility’s approved rates recover only reasonable utility system costs,” said Munashe Magarira, a senior attorney with the Southern Environmental Law Center. “More importantly, they represent a missed opportunity to more comprehensively address the cost-of-living crisis and advance the clean energy transition head on.”
The groups also say the orders approve a cost-recovery framework that puts a disproportionate share of grid costs on residential customers. They welcomed the data-center tariff but say it applies to only a subset of large-load customers, and that whether data centers pay their fair share of grid upgrades has been deferred to the stakeholder process.
Consumer Reports, which says more than 13,000 North Carolinians spoke out against the request, called the decision disappointing. “This final order asks hard working North Carolinians to sacrifice financially by paying over 9% more for electricity, while protecting Duke’s excessive profits,” said Chris Harto, the organization’s manager of energy policy. Consumer Reports also praised the order’s data-center protections, while saying “the devil will be in the details.”
The advocates also raised a separate concern: the Customer Assistance Program, which helps struggling customers with their bills, could end, leaving 87,000 customers facing a $52 jump in their bills come January 1, according to the North Carolina Justice Center. “We call on Duke Energy to request the NC Utilities Commission’s approval to extend the Customer Assistance Program and not let 87,000 customers’ bills jump $52 come January 1,” said Claire Williamson, senior energy policy advocate at the North Carolina Justice Center. Attorney General Jeff Jackson did not sign the Duke Energy Progress settlement.
A second decision the same day
In a separate order, the commission also approved Duke Energy’s updated Carbon Plan and Integrated Resource Plan, the long-term blueprint for meeting growing electricity demand. The plan extends the retirement dates of some coal-fired power plants, calls for about 3,841 megawatts of new natural gas generation between 2030 and 2033, and authorizes up to $440 million for new nuclear development options. Four commissioners approved the order unanimously; Commissioner Donald van der Vaart did not participate.
It is the first Carbon Plan decision since state lawmakers eliminated the interim requirement to cut power-sector carbon emissions 70 percent by 2030, leaving the net-zero-by-2050 target in place. Duke Energy has said the projected cost of its 2025 resource plan over the next decade is nearly half that of the plan regulators approved in 2024, citing changes in state and federal policy. The company is expected to file its next proposed Carbon Plan in fall 2027.
The Southern Environmental Law Center, which intervened in the Carbon Plan case, said the plan “puts North Carolinians at risk of increasing energy bills for polluting methane gas plants while underinvesting in the clean energy resources that are needed to meet state law requirements.”