The North Carolina Department of Transportation expects most of the work to widen I-85 between McAdenville and Belmont to be finished in 2031, according to sources.
NCDOT laid out the timeline for regional transportation leaders recently. The project adds one lane in each direction between Exit 17 (U.S. 321) in Gastonia and Exit 27 (N.C. 273) in Belmont, widening about 10 miles of the interstate from six lanes to eight.
“There is a daily backup heading south,” NCDOT’s Mark Stafford told the group, WCNC reported.
The first section runs about four miles from N.C. 7 (Exit 23) to N.C. 273 (Exit 27) at the Catawba River. NCDOT awarded Lane Construction Corp. a $337 million design-build contract for it in July 2025. The work includes new bridges at Exits 23 and 27, replacing or rehabilitating the I-85 bridge over the South Fork Catawba River, and changes to the N.C. 7/Wilkinson Boulevard intersection.
The western section, from Exit 23 to U.S. 321 in Gastonia, is set to go out for bids in late 2028, according to NCDOT. A third section, which replaces three railroad bridges and the Groves Street bridge in Lowell, is expected to take until 2033. NCDOT’s current estimate for the full stretch is $1.4 billion, according to WCNC.
Drivers get a break for the holidays. NCDOT says there will be no construction lane closures on the corridor from 4 p.m. to midnight each day through January 2. Most of the work is done at night.
Sources: WCNC; NCDOT