State Auditor Releases Accounting of Charlotte’s $650 Million Stadium Investment

The North Carolina State Auditor’s Office has released its first report on the City of Charlotte’s $650 million public financing for renovations to Bank of America Stadium, detailing how the first $3.1 million has been spent.

The report, the first in a planned series tracking the public money, says that as of August 2026 the city had authorized and funded about $3.1 million in project-related disbursements: $2,528,684 for construction and $632,656 in debt-financing costs.

The construction spending so far has gone toward ongoing work on the Panthers Field House. The largest share, $1,094,290, went to building structure and exterior work, including structural steel, roofing and insulation, masonry, framing and fireproofing. Another $711,726 went to mechanical, electrical and plumbing work, including HVAC equipment and electrical rough-in. Construction management and coordination accounted for $562,845, site, landscape and infrastructure work for $326,776, and professional, design, consulting and testing services for $64,491. The city withheld $231,444 in retainage, construction payments held back based on contract terms and progress.

The financing costs covered legal services ($298,160), financial advisory services ($255,096), credit-rating services ($42,400), trustee and agent services ($24,000), and offering-document costs ($13,000).

The report puts the first spending in the context of the larger project. The overall renovation cost is $1.3 billion. The city plans to contribute up to $650 million, approved by the Charlotte City Council in a 7-3 vote in June 2024, with Tepper Sports & Entertainment committing $150 million under its agreement with the city, also announcing an additional $500 million investment in July 2026.

The city plans to repay project debt with revenues from Mecklenburg County’s occupancy tax and prepared food and beverage tax. The North Carolina Local Government Commission unanimously approved the city’s financing request in April 2026, and the improvements are expected to be completed by 2030.

The agreement keeps the Carolina Panthers and Charlotte FC in Charlotte through 2040, with a financial obligation encouraging the teams to stay through early 2046. The stadium now hosts about 50 ticketed events a year and roughly two million attendees annually, including, in recent years, a Copa America semifinal, two sold-out Savannah Bananas nights, the 2026 MLS All-Star game, and the Concert for Carolina, which raised $24.5 million for Hurricane Helene relief. City-funded elements most visible to visitors are slated to include a new social patio on the stadium’s 500 level with city views.

State Auditor Dave Boliek’s office notes two things readers should know about this first report: it is an informational overview, not an audit conducted under government auditing standards, and the spending categories were designed with assistance from CoPilot and assigned by professional judgment. Future reports are expected to provide independently reviewed information on borrowing, expenditures, construction progress, significant changes, and oversight results — a continuing public account of how the $650 million is managed.

The full report is available from the State Auditor’s Office here.